PLANNING A MULTI-UNIT TURNAROUND
Executing a turnaround across multiple petrochemical processing units requires months of detailed pre-planning before the first valve is closed. Our project management team developed over 120 individual work packs, each containing task-level instructions, material requirements, and resource assignments. Pre-turnaround workshops brought together operations, maintenance, and HSE stakeholders to walk through every critical path activity and identify potential bottlenecks before they could impact the schedule.